General Projects

Bryan Midtown Park Improvements

City Job No. 700-D0-1712/572-D1-1811

This project is to provide improvements to the park.

Bryan Midtown Park Project Map in PDF Format

General Information

 

  • Project Manager/City Contact: Frank Clark
  • Alternate City Contact: Paul Kaspar, P.E., C.F.M.

Design

  • Funding Source: Capital Reserve Fund
  • Design Engineer: Mitchell & Morgan
  • Contract Amount: $2,622,79.05

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2002
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $2,756,991.50
  • City Inspector: Mike Nobles
  • Status: Phase 1B & 3A are complete. This will stay until total project is complete.

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2013
  • Contractor: Construction Rent-A-Fence
  • Contract Amount: $37,166.25
  • City Inspector: Alan Mitchell
  • Status: Phase 1C is complete. This will stay until total project is complete.

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2011
  • Contractor: Kelly Burt Dozer
  • Contract Amount: $719,901.58
  • City Inspector: Mike Nobles
  • Status: Phase 3E is complete. This will stay  until total project is complete.

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2017
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $3,667,960.00
  • City Inspector: Alan Mitchell
  • Status: Phase 3C is complete. This will stay until total project is complete.

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2010
  • Contractor: Solitude Lake Management
  • Contract Amount: $45,000
  • City Inspector: Mike Nobles
  • Status: Phase 3B is complete. This will stay until total project is complete.

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2003
  • Contractor: Marek Bros Construction, Inc.
  • Contract Amount: $544,000.40
  • City Inspector: Mike Nobles
  • Status: Phase 1D is complete. This will stay  until total project is complete.

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2010
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $1,148,190.95
  • City Inspector: Alan Mitchell
  • Status: Phase 2 is complete. This will stay until total project is complete.
  • Updated:02/27/23

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2024
  • Contractor: Palasota Contracting LLC
  • Contract Amount: $2,053,110.20
  • City Inspector: Alan Mitchell
  • Status: 3D is approximately 93% complete.
  • Updated:03/13/24

 

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2029
  • Contractor: Larry Young Paving, LLC.
  • Contract Amount: $4,996,227.06
  • City Inspector: Alan Mitchell
  • Status: Phase 5A -Midtown Blvd is complete. This will stay until total project is complete.
  • Updated: 08/01/22

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2011
  • Contractor: Norman Construction Services, LLC.
  • Contract Amount: $1,039,439.00
  • City Inspector: Alan Mitchell
  • Status: Phase 3E is complete. This will stay until total project is complete.
  • Updated: 03/13/24

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2219
  • Contractor: Walker Partners
  • Contract Amount: $123,850.00
  • City Inspector: Alan Mitchell
  • Status:  Bid opening for this project is set for March 19, 2024. The anticipated recommendation for contract award is to be presented at the April City Council Meeting.  Anticipated completion of this project is December 24′ – January 25′
  • Updated: 03/13/2024

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700-D0-2210
  • Contractor: Caffey & Sons, Inc.
  • Contract Amount: $488,640.00
  • City Inspector: Alan Mitchell
  • Status: Phase 9c – Monument Signage – Construction is approximately 96% complete.
  • Updated: 03/13/24

Construction

  • Funding Source: 2020 Bonds-Fund 374
  • City Job No. 700 -D0-2208
  • Contractor: Brazos Paving, Inc.
  • Contract Amount: $7,853,697.77
  • City Inspector: Alan Mitchell
  • Status: Ph 8A – Road A – Approximately 85% of the street and 70% of the parking lot have been poured. Completion of the parking lots is anticipated within the next two months.
  • Updated: 03/13/24

Design/Build

  • Funding Source: General Fund/The Darwood Foundation
  • City Job No. 700 -D0-2323
  • Contractor: SpawGlass
  • Contract Amount: $4,500,000.00
  • City Inspector: Alan Mitchell
  • Status: In Design
  • Updated: 03/13/24

Railroad Quiet Zones Streetscaping

City Job No. 332-D3-1108

This project is to provide safety and acoustical improvements along the railroad corridor in Bryan.

General Information

  • Project Manager/City Contact: Rachel Gaddis, E.I.T.
  • Alternate City Contact: Paul Kaspar, P.E., C.F.M.

Design

  • Funding Source: Transportation Fund
  • Design Engineer: CTC, Inc.
  • Contract Amount: $22,698.00
  • Status: Complete

Construction

  • Funding Source: General Fund Bonds
  • CIP Budget: $5,517,000.00
  • Contractor: Brazos Paving, Inc.
  • Contract Amount: $657,991.00
  • City Inspector: Kurk Fowler
  • Status: Approximately 60% complete.  Awaiting approval from UPRR to work in the UPRR Right – Of – Way.
  • Updated: 03/13/24

 

Gateway Monument Sign

 

City Job No. 700-DE-1712 – Gateway Monument Signage

This project will install two new gateway monument signs for the City of Bryan located in the following areas: along Hwy 6 between TX-OSR and Louis E Mikulin Rd, and along Hwy 21 at the northwest corner of the RELLIS campus.

 

General Information

  • Project Manager/City Contact: Eric Blackburn, EIT
  • Alternate City Contact:  Paul Kaspar, P.E., C.F.M.

Design

  • Funding Source: General Fund
  • Design Engineer: RVI Planning & Landscape Architecture, Inc.
  • Contract Amount: $23,600.00
  • Status: Complete

Construction

  • Funding Source:  General Fund
  • City Job No. 700 -DE-1712
  • Contractor: Kubacak Construction, LLC.
  • Contract Amount:  $336,620.96
  • City Inspector: Michael Oliver
  • Status:  Construction is approximately 50% complete.
  • Updated: 03/14/24