General Projects
Bryan Midtown Park Improvements
City Job No. 700-D0-1712/572-D1-1811
This project is to provide improvements to the park.
Bryan Midtown Park Project Map in PDF Format
General Information
- Project Manager/City Contact: Frank Clark
Design
- Funding Source: Capital Reserve Fund
- Design Engineer: Mitchell & Morgan
- Contract Amount: $2,622,79.05
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2002
- Contractor: Palasota Contracting LLC
- Contract Amount: $2,756,991.50
- City Inspector: Mike Nobles
- Status: Phase 1B & 3A – Bomber Drive & Deceleration Lane are complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2013
- Contractor: Construction Rent-A-Fence
- Contract Amount: $37,166.25
- City Inspector: Alan Mitchell
- Status: Phase 1C – Travis Field is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2003
- Contractor: Marek Bros Construction, Inc.
- Contract Amount: $544,000.40
- City Inspector: Mike Nobles
- Status: Phase 1D – Gateway Landscaping is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2010
- Contractor: Palasota Contracting LLC
- Contract Amount: $1,148,190.95
- City Inspector: Alan Mitchell
- Status: Big Shots Access Driveway is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2011
- Contractor: Kelly Burt Dozer
- Contract Amount: $719,901.58
- City Inspector: Mike Nobles
- Status: Big Shots Detention Pond is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2010
- Contractor: Solitude Lake Management
- Contract Amount: $45,000
- City Inspector: Mike Nobles
- Status: Phase 3B – Fish Relocation is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2017
- Contractor: Palasota Contracting LLC
- Contract Amount: $3,667,960.00
- City Inspector: Alan Mitchell
- Status: Phase 3C – Lake Earthwork is complete. This will stay until total project is complete.
Design
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2219
- Contractor: Walker Partners
- Contract Amount: $123,850.00
- City Inspector: Alan Mitchell
- Status: Phase 3C-2 – Boardwalk – Design is complete.
Construction
- Funding Source: Fund 377 – 2026 Bonds
- City Job No. 700 -D0-2219
- Contractor: Bartlett Cocke General Contractors
- Contract Amount: $4,198,152.34
- City Inspector: Alan Mitchell
- Status: Phase 3C-2 – Boardwalk – Construction is 65% complete. Large rain storms since the beginning of construction in March 2025 have caused a slight delay in progress.
- Updated: 9/22/2025
Construction
- Funding Source: Fund 377 – 2026 Bonds
- City Job No. 700 -D0-2117
- Contractor: Larry Young Paving
- Contract Amount: $5,637,052.05
- City Inspector: Alan Mitchell
- Status: Phase 3C-3 – Dam & Spillway – Construction is approximately 1% complete.
- Updated: 9/22/2025
Construction
- Funding Source: Fund 377 – 2026 Bonds
- City Job No. 700 -D0-2209
- Contractor: Brien Water Wells
- Contract Amount: $1,537,139.85
- City Inspector: Alan Mitchell
- Status: Phase 3C-4 – Water Wells – Drilling of the pilot hole has been completed, and water quality samples have been collected. City staff is currently coordinating with TCEQ to verify whether the water quality results fall within the parameters of the City’s existing TCEQ water rights permit.
- Updated: 9/22/2025
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2024
- Contractor: Palasota Contracting LLC
- Contract Amount: $2,053,110.20
- City Inspector: Alan Mitchell
- Status: Phase 3D – Outer Loop Trail – Construction is substantially complete.
- Updated: 9/22/2025
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2011
- Contractor: Norman Construction Services, LLC.
- Contract Amount: $1,039,439.00
- City Inspector: Alan Mitchell
- Status: Phase 3E – Carson St Detention Pond is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2029
- Contractor: Larry Young Paving, LLC.
- Contract Amount: $4,996,227.06
- City Inspector: Alan Mitchell
- Status: Phase 5A -Midtown Blvd is complete. This will stay until total project is complete.
Design/Construction
- Funding Source: General Fund
- City Job No. 700 -D0-2323
- Contractor: SpawGlass
- Contract Amount: $4,500,000.00
- City Inspector: Alan Mitchell
- Status: Phase 5D – Playground – In Design. Staff await approval of conceptual design/cost.
- Updated: 9/22/2025
Construction
- Funding Source: General Fund
- City Job No. 700-D0-2208
- Contractor: Brazos Paving Inc.
- Contract Amount: $7,853,697.77
- City Inspector: Alan Mitchell
- Status: Phase 8A- Road A – is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2210
- Contractor: Caffey & Sons, Inc.
- Contract Amount: $488,640.00
- City Inspector: Alan Mitchell
- Status: Phase 9C – Marquee Signage is complete. This will stay until total project is complete.
Railroad Quiet Zones Streetscaping
City Job No. 332-D3-1108
This project is to provide safety and acoustical improvements along the railroad corridor in Bryan.
Phase 1 includes improvements to 7 Downtown Bryan railroad crossings at E. 29th St, E. 28th St, 26th St, William J. Bryan Parkway, 24th St, 23rd St, & Martin Luther King Jr St. Construction for Phase 1 was completed in January 2025.
Phase 2 includes improvements to Downtown Bryan railroad crossings at Sims Ave, Groesbeck St, Graham St, Pease St, Parker St, W. 29th St, W.28th St., & pedestrian improvements near the Clara B. Mounce Public Library.
General Information
- Project Manager/City Contact: Eric Blackburn, E.I.T.
Design Phase 1
- Funding Source: Transportation Fund
- Design Engineer: CTC, Inc.
- Contract Amount: $22,698.00
- Status: Complete
Design Phase 2
- Funding Source:
- Design Engineer:
- Contract Amount:
- Status: In progress. Initial design set is being reviewed by Union Pacific Rail Road.
- Updated: 9/22/2025
Construction Phase 1
- Funding Source: General Fund Bonds
- CIP Budget: $5,517,000.00
- Contractor: Brazos Paving, Inc.
- Contract Amount: $657,991.00
- City Inspector: Kurk Fowler
- Status: Complete
Construction Phase 2
- Funding Source: TBD
- CIP Budget: TBD
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
- Status: In Design
Briarcrest Dr Traffic Signals
City Job No. 750-D7-1816
This project will improve traffic signals at Briarcrest Dr at Broadmoor Dr and Briarcrest Dr at Villa Maria Rd.
General Information
- Project Manager/City Contact: Zachary Kennard, P.E., RSP1
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer: Binkley & Barfield
- Contract Amount: $59,600.00
- Status: Complete
Construction
- Funding Source: Fund 240 – Street Fund
- City Job No. 750-D7-1816
- Contractor: Bayer Construction
- Contract Amount: $1,012,726.48
- City Inspector: Alan Mitchell
- Status: Complete
E 29th St Traffic Signals Phase 2
City Job No. 750-D7-2403
This project will improve traffic signals at East 29th Street at Still Meadow Drive and East 29th Street at Barak Lane.
General Information
- Project Manager/City Contact: Elizabeth Pedersen, E.I.T.
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer: Kimley Horn & Associates
- Contract Amount: $124,235.00
- Status: 100% plan set submittal in progress. Contract amount is for contractor services relating to 2 projects – 29th St Traffic Signals Ph 2 and South College at North Ave Traffic Signal.
- Updated: 9/22/2025
Construction
- Funding Source: Fund 240 – Street Fund
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
2024 Major Corridor Signal Timing
City Job No. 750-D7-2413
General Information
- Project Manager/City Contact: Uday Kari, P.E., PTOE
- Secondary City Contact: Zachary Kennard, P.E., RSP1
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer: TBD
- Contract Amount: TBD
- Status: Traffic Operations is working on an in-house traffic data collection plan prior to moving forward with retiming.
- Status: 9/22/2025
Construction
- Funding Source: Fund 240 – Street Fund
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
South College and North Ave Traffic Signal
City Job No. 750-D7-2409
This project will improve traffic signal located at the intersection of North Avenue and South College Avenue.
General Information
- Project Manager/City Contact: Elizabeth Pedersen, E.I.T.
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer: Kimley Horn & Associates
- Contract Amount: $124,235.00
- Status: 100% plan set submittal in progress. Contract amount is for contractor services relating to 2 projects: 29th St Traffic Signals Ph 2 and South College at North Ave Traffic Signal.
- Updated: 9/22/2025
Construction
- Funding Source: Fund 240 – Street Fund
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
Trafalgar Traffic Signals
City Job No. 750-D7-2412
This includes the design and construction of traffic signals at the intersection of Miramont Blvd at Boonville Rd and the intersection of Green Valley Dr and Briarcrest Dr.
General Information
- Project Manager/City Contact: Zachary Kennard, P.E., RSP1
Design
- Funding Source: Fund 377 – 2026 Bond Fund
- Design Engineer: KCI
- Contract Amount: $125,368.00
- Status: Design firm has begun work. Design of Miramont and Boonville signal to be prioritized in order to honor development agreement with adjacent site. Design of Miramont at Boonville to be completed by early November.
Construction
- Funding Source: TBD
- City Job No. TBD
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
Finfeather Road at Dodge Street Traffic Signal
City Job No. 750-D7-2430
This project will improve a traffic signal located at the intersection of Finfeather Rd & W. Dodge St.
General Information
- Project Manager/City Contact: Zachary Kennard, P.E., RSP1
Design
- Funding Source: N/A
- Design Engineer: City of Bryan Engineering Services
- Contract Amount: N/A
- Status: Plan set has been submitted to TxDOT and Union Pacific Railroad for review.
- Updated: 9/22/2025
Construction
- Funding Source: TBD
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD