Downtown Quiet Zone
The Navasota Subdivision enters the City of Bryan from the west and then turns south near 28th Street and Bryan Ave. The Quiet Zone will span from W. 28th Street to W. Pease Street on this track.
This project has been broken into three phases:
- Phase 1: Bryan Subdivision
- Phase 2: Navasota Subdivision
- Phase 3: Groesbeck Crossing
Once the improvements to all three phases of the Downtown Quiet Zone are completed and approved by the FRA, trains will no longer sound at these crossings.
Do you want to see the proposed improvements at each intersection? Our GIS Story Map can show you that and a whole lot more. We will walk you through the planned improvements at each crossing and show progress update photos in a neat before and after feature. Here you can also find the overall planned sequence and schedule for construction.
Latest Updates
Timeline
Phase 1: Bryan Subdivision
Construction is expected to begin on Aug. 9, 2021 and is estimated to take six to eight months, weather permitting. This schedule is subject to change.
Varying improvements, including medians, islands, sidewalks, striping, signage and gate arm improvements are planned for the following intersections:
Outside of Railroad ROW
E. 29th Street
Start: Aug. 9
End: Aug. 27E. 28th Street
Start: Aug. 11
End: Sept. 2E. 26th Street
Start: Sept. 3
End: Sept. 27E. 24th Street
Start: Sept. 7
End: Sept. 23E. 23rd Street
Start: Sept. 24
End: Oct. 13E. 22nd Street
Start: Sept. 28
End: Oct. 18E. Martin Luther King Jr. Street
Start: Oct. 19
End: Nov. 4E. 15th Street
Start: Oct. 19
End: Nov. 15Inside of Railroad ROW
E. 15th Street
Start: Nov. 16
End: Nov. 23E. Martin Luther King Jr. Street
Start: Nov. 24
End: Jan. 5, 2022E. 22nd Street
Start: Jan. 6, 2022
End: Jan. 13, 2022E. 23rd Street
Start: Jan. 14, 2022
End: Jan. 25, 2022E. 24th Street
Start: Jan. 14, 2022
End: Jan. 25, 2022William Joel Bryan Parkway
Start: Jan. 14, 2022
End: Jan. 27, 2022E. 26th Street
Start: Jan. 28, 2022
End: Feb. 8, 2022E. 28th Street
Start: Jan. 28, 2022
End: Feb. 8, 2022E. 29th Street
Start: Jan. 28, 2022
End: Feb. 8, 2022W. 32nd Street
Start: Feb. 22, 2022
End: March 11, 2022In addition to the intersections above, a wayside horn will be installed at Pease Street. This provides directional warning to oncoming traffic to warn of an approaching train. The installation of this mechanism is to be completed outside the Phase 1 contract with Brazos Paving, Inc.
Phase 2: Navasota Subdivision
Construction could begin before the end of 2021 and is expected to take six months.
Varying improvements, including medians, islands, sidewalks, striping, signage and gate arm improvements are planned for the following intersections:
- W. 29th Street
- S. Bryan Avenue
- W. 28th Street
- S.Parker Avenue
- S. Sims Street
- Pedestrian walkway between the Clara B Mounce and Carnegie Libraries
- S. Reed Street
- Brazos Avenue
- Graham Road
Phase 3: Groesbeck Crossing
The design for the intersection improvements have been completed. The improvements include minor realignment, the addition of sidewalks, and a signal on both sides of the train tracks. There is not currently a timeline for construction of this phase, as that is contingent upon Union-Pacific Railroad approving documentation and making trackside improvements.
Still Have Questions?
If you still have questions, or would like more information about the Downtown Quiet Zone project, please contact:
Rachel Gaddis, EIT
Phone: 979.209.5030
Email: rgaddis@bryantx.gov