Drainage Projects
Drainage Projects
- Still Creek Culvert Replacement
- Bristol St & Esther Blvd Drainage Improvements
- Hillside Oaks and Old Oaks Drainage Improvements
- Wayside and Carter Creek Storm Sewer Rehabilitation
- S College Ave Stormwater Detention Pond
- Carriage Hills Detention Pond
Flood Studies
Drainage Projects
Still Creek Culvert Replacements
City Job No. 425-D1-1805
This project is the analysis, design, and construction of culverts at four locations in the Still Creek Drainage Basin to decrease the floodplain elevation and lessen the impact of the floodwaters on the adjacent residences. Project will close Missouri t Bonham Park and remove box culverts at that location. Extend Missouri between Yellowstone and Wilkes.
Still Creek Project Map in PDF Format
General Information
- Project Manager/City Contact: Patricia Edwards, P.E.
- Alternate City Contact: Sam Vernon, P.E., C.F.M.
Design
- Funding Source: Drainage Fee
- Design Engineer: Mitchell and Morgan
- Contract Amount: $179,665.00
- Status: Project scope was revised to include the closing of Missouri at Bonham Park and removing box culverts at that location, and includes the extension of Missouri between Yellowstone and Wilkes.
Construction
- CIP Budget: $2,400,000.00
- Funding Source: Transportation Fee; Drainage Fee
- Contractor: Palasota Contracting
- Contract Amount: $1,653,994.00
- City Inspector: Alan Mitchell
- Status: This project complete.
- Updated: 04/26/22
Bristol St & Esther Blvd Drainage Improvements
City Job No. 425-D2-1910
This contract will include, replacement of existing storm sewer collection system to increase capacity to Burton Creek, new storm sewers to be installed within existing right-of-ways. Reconstruction of concrete streets where new storm sewer will be installed, resizing and addition of storm inlets to increase capture capacity, and 2D modeling.
Bristol & Esther Project Map in PDF Format
General Information
- Project Manager/City Contact: Kelly Sullivan, P.E.
- Alternate City Contact: Sam Vernon, P.E., C.F.M.
- Public Meeting: First Presentation – July 8, 2020
- Neighborhood Feedback: Give Us Your Input on This Project
Design
- Funding Source: Drainage Fee
- Design Engineer: Walker Partners LLC
- Contract Amount: $354,500.00
- Status: Design is complete. Project is planned to bid in late 2023.
- Updated: 10/13/22
Construction
- CIP Budget: TBD
- Funding Source: Drainage Fee
- Contractor: TBD
- Contract Amount: $ TBD
- City Inspector: TBD
- Status:
- Updated:
Hillside Oaks & Old Oaks Drainage Improvements
General Information
- Project Manager/City Contact: Kelly Sullivan, P.E.
- Alternate City Contact: Sam Vernon, P.E., C.F.M.
Design
- Funding Source: Drainage Fee
- Design Engineer: Goodwin Lasiter Strong
- Contract Amount:$236,500
- Status: Complete
- Updated: 10/13/23
Construction
- Funding Source: Drainage Fee
- Contractor: Texcon General Contractors
- Contract Amount: $3,049,293.00
- City Inspector: Michael Oliver
- Status: Project started construction August 2023, with an estimated completion date in Summer 2024.
- Updated: 10/13/23
Wayside and Carter Creek Storm Rehab
City Job No. 425-D1-2028 Wayside and Carter Creek Storm Rehab
This project includes the analysis of and improvements to storm water infrastructure in various locations near Wayside Drive and Carter Creek Parkway.
General Information
- Project Manager/City Contact: Brianna Groves, P.E., CFM
Design
- Funding Source: General Fund
- Design Engineer: Gessner Engineering
- Contract Amount: $110,000
- Status: Staff reviewed the preliminary engineering report (PER) and provided questions and comments to the designer to ensure that the drainage issues in the area are properly identified. A public meeting is being scheduled for December, where the PER will be finalized and conceptual plan sheets will be available for residents to review and provide feedback on.
- Updated: 10/13/23
Construction
- Funding Source: General Fund
- City Job No. 425-D1-2028
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
- Status:
- Updated:
South College Avenue Stormwater Detention Pond
City Job No. 425-DE-2016
General Information
- Project Manager/City Contact: Brianna Groves, P.E., C.F.M
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: 2022 Bond Fund
- Design Engineer: Goodwin Lasiter Strong
- Contract Amount:$417,600
- Status: Complete
- Updated: 10/13/23
Construction
- Funding Source: 2022 Bond Fund
- Contractor: Norman Construction Services
- Contract Amount: $869,427
- City Inspector: Alan Mitchell
- Status: Construction is 65% complete.
- Updated: 10/13/23
Carriage Hills Detention Pond
City Job No. 425-D2-2217
General Information
- Project Manager/City Contact: Eric Blackburn, E.I.T.
- Alternate City Contact: Paul Kaspar, P.E., C.F.M.
Design
- Funding Source: Drainage Utility Fund – Fund 245
- Design Engineer: Goodwin Lasiter Strong
- Contract Amount:$13,100
- Status: Complete
- Updated: 10/13/23
Construction
- Funding Source: Drainage Utility Fund – Fund 245
- Contractor: Norman Construction Services
- Contract Amount: $228,150
- City Inspector: Kurk Fowler
- Status: Contract was awarded on 10/10/23. Project is estimated to be complete by December 2023.
- Updated: 10/13/23
Briar Creek Floodplain Modeling
City Job No. 425-D1-0004
Through this contract, the Consultant will update the rainfall and runoff generation (hydrologic) and floodplain (hydraulic) modeling for Briar Creek, using updated topographic information as well as more accurate information related to the Carter’s Creek floodplain which significantly affects this watershed. The results of the updated models will be provided to FEMA for the Letter of Map Revision (LOMR) process to update the community Flood Insurance Rate Maps.
Briar Creek Project Map in PDF Format
General Information
- Project Manager/City Contact: Paul Kaspar, P.E., C.F.M.
Design
-
- Funding Source: Drainage Fee
- Design Engineer: Mitchell & Morgan
- Contract Amount: $32,200.00
- Status: FEMA Submittal.
- Updated: 03/07/2022