General Projects
Bryan Midtown Park Improvements
City Job No. 700-D0-1712/572-D1-1811
This project is to provide improvements to the park.
Bryan Midtown Park Project Map in PDF Format
General Information
- Project Manager/City Contact: Frank Clark
Design
- Funding Source: Capital Reserve Fund
- Design Engineer: Mitchell & Morgan
- Contract Amount: $2,622,79.05
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2002
- Contractor: Palasota Contracting LLC
- Contract Amount: $2,756,991.50
- City Inspector: Mike Nobles
- Status: Phase 1B & 3A – Bomber Drive & Deceleration Lane are complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2013
- Contractor: Construction Rent-A-Fence
- Contract Amount: $37,166.25
- City Inspector: Alan Mitchell
- Status: Phase 1C – Travis Field is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2003
- Contractor: Marek Bros Construction, Inc.
- Contract Amount: $544,000.40
- City Inspector: Mike Nobles
- Status: Phase 1D – Gateway Landscaping is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2010
- Contractor: Palasota Contracting LLC
- Contract Amount: $1,148,190.95
- City Inspector: Alan Mitchell
- Status: Big Shots Access Driveway is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2011
- Contractor: Kelly Burt Dozer
- Contract Amount: $719,901.58
- City Inspector: Mike Nobles
- Status: Big Shots Detention Pond is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2010
- Contractor: Solitude Lake Management
- Contract Amount: $45,000
- City Inspector: Mike Nobles
- Status: Phase 3B – Fish Relocation is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2017
- Contractor: Palasota Contracting LLC
- Contract Amount: $3,667,960.00
- City Inspector: Alan Mitchell
- Status: Phase 3C – Lake Earthwork is complete. This will stay until total project is complete.
Design
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2219
- Contractor: Walker Partners
- Contract Amount: $123,850.00
- City Inspector: Alan Mitchell
- Status: Phase 3C-2 – Boardwalk – Project is in the construction phase.
- Updated: 6/9/2025
Construction
- Funding Source: Fund 377 – 2026 Bonds
- City Job No. 700 -D0-2219
- Contractor: Bartlett Cocke General Contractors
- Contract Amount: $4,198,152.34
- City Inspector: Alan Mitchell
- Status: Phase 3C-2 – Boardwalk – Construction is 15% complete. Large rain storms since the beginning of construction in March 2025 have caused a slight delay in progress.
- Updated: 6/9/2025
Design
- Funding Source: TBD
- City Job No. 700 -D0-2117
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: Alan Mitchell
- Status: Phase 3C-3 – Dam & Spillway – The construction services contract has been signed and the city is reviewing construction materials to be used by the contractor. The project is expected to begin construction in Summer of 2025.
- Updated: 6/9/2025
Construction
- Funding Source: Fund 377 – 2026 Bonds
- City Job No. 700 -D0-2209
- Contractor: Brien Water Wells
- Contract Amount: $1,537,139.85
- City Inspector: Alan Mitchell
- Status: Phase 3C-4 – Water Wells – Site No. 2 is prepped and ready for drilling. However, contractor has not started drilling. Project is on schedule.
- Updated: 6/9/2025
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2024
- Contractor: Palasota Contracting LLC
- Contract Amount: $2,053,110.20
- City Inspector: Alan Mitchell
- Status: Phase 3D – Outer Loop Trail – Construction is substantially complete.
- Updated: 6/9/2025
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2011
- Contractor: Norman Construction Services, LLC.
- Contract Amount: $1,039,439.00
- City Inspector: Alan Mitchell
- Status: Phase 3E – Carson St Detention Pond is complete. This will stay until total project is complete.
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2029
- Contractor: Larry Young Paving, LLC.
- Contract Amount: $4,996,227.06
- City Inspector: Alan Mitchell
- Status: Phase 5A -Midtown Blvd is complete. This will stay until total project is complete.
Design/Construction
- Funding Source: General Fund
- City Job No. 700 -D0-2323
- Contractor: SpawGlass
- Contract Amount: $4,500,000.00
- City Inspector: Alan Mitchell
- Status: Phase 5D – Playground – In Design. Staff await approval of conceptual design/cost.
- Updated: 6/9/2025
Construction
- Funding Source: General Fund
- City Job No. 700-D0-2208
- Contractor: Brazos Paving Inc.
- Contract Amount: $7,853,697.77
- City Inspector: Alan Mitchell
- Status: Phase 8A- Road A – is complete. This will stay until total project is complete.
- Updated: 6/9/2025
Construction
- Funding Source: Fund 374 – 2020 Bonds
- City Job No. 700-D0-2210
- Contractor: Caffey & Sons, Inc.
- Contract Amount: $488,640.00
- City Inspector: Alan Mitchell
- Status: Phase 9C – Marquee Signage is complete. This will stay until total project is complete.
Railroad Quiet Zones Streetscaping
City Job No. 332-D3-1108
This project is to provide safety and acoustical improvements along the railroad corridor in Bryan.
Phase 1 includes improvements to 7 Downtown Bryan railroad crossings at E. 29th St, E. 28th St, 26th St, William J. Bryan Parkway, 24th St, 23rd St, & Martin Luther King Jr St. Construction for Phase 1 was completed in January 2025.
Phase 2 includes improvements to Downtown Bryan railroad crossings at Sims Ave, Groesbeck St, Graham St, Pease St, Parker St, W. 29th St, W.28th St., & pedestrian improvements near the Clara B. Mounce Public Library.
General Information
- Project Manager/City Contact: Eric Blackburn, E.I.T.
Design Ph 1
- Funding Source: Transportation Fund
- Design Engineer: CTC, Inc.
- Contract Amount: $22,698.00
- Status: Complete
Design Ph 2
- Funding Source:
- Design Engineer:
- Contract Amount:
- Status: In progress. Initial design set is being reviewed by Union Pacific Rail Road.
- Updated: 6/9/2025
Construction Phase 1
- Funding Source: General Fund Bonds
- CIP Budget: $5,517,000.00
- Contractor: Brazos Paving, Inc.
- Contract Amount: $657,991.00
- City Inspector: Kurk Fowler
- Status: Complete
- Updated: 6/9/2025
Construction Phase 2
- Funding Source: TBD
- CIP Budget: TBD
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
- Status: In Design
- Updated: 6/9/2025
Briarcrest Dr Traffic Signals
This project will improve traffic signals at Briarcrest Dr at Broadmoor Dr and Briarcrest Dr at Villa Maria Rd.
City Job No. 750-D7-1816
General Information
- Project Manager/City Contact: Zachary Kennard, P.E.
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer: Binkley & Barfield
- Contract Amount: $59,600.00
- Status: Complete
Construction
- Funding Source: Fund 240 – Street Fund
- City Job No. 750-D7-1816
- Contractor: Bayer Construction
- Contract Amount: $1,012,726.48
- City Inspector: Alan Mitchell
- Status: Flatwork and signal work are complete. Contractor finishing the last few items on the punchlist.
- Updated: 6/9/2025
E 29th St Traffic Signals Phase 2
City Job No. 750-D7-2403
This project will improve traffic signals at East 29th Street at Still Meadow Drive and East 29th Street at Barak Lane.
General Information
- Project Manager/City Contact: Elizabeth Pedersen, E.I.T.
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer: Kimley Horn & Associates
- Contract Amount: $124,235.00
- Status: 60% submittal sent out for review. Comments returned to design engineer on 3/25/2025. Contract amount is for contractor services relating to 2 projects – 29th St Traffic Signals Ph 2 and South College at North Ave Traffic Signal.
Construction
- Funding Source: Fund 240 – Street Fund
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
- Status:
- Updated: 6/9/2025
2024 Major Corridor Signal Timing
City Job No. 750-D7-2413
General Information
- Project Manager/City Contact: Zachary Kennard, P.E.
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer:
- Contract Amount:
- Status: Paused negotiation. Traffic Operations Supervisor would like to install new Advanced Traffic Signal Performance Measures (ATSPM) technology prior to performing any retiming.
Construction
- Funding Source: Fund 240 – Street Fund
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
- Status: 6/9/2025
South College and North Ave Traffic Signal
City Job No. 750-D7-2409
This project will improve traffic signal located at the intersection of North Avenue and South College Avenue.
General Information
- Project Manager/City Contact: Elizabeth Pedersen, E.I.T.
Design
- Funding Source: Fund 240 – Street Fund
- Design Engineer: Kimley Horn & Associates
- Contract Amount: $124,235.00
- Status: 60% submittal sent out for review. Comments returned to design engineer on 3/25/2025. Contract amount is for contractor services relating to 2 projects: 29th St Traffic Signals Ph 2 and South College at North Ave Traffic Signal.
Construction
- Funding Source: Fund 240 – Street Fund
- Contractor: TBD
- Contract Amount: TBD
- City Inspector: TBD
- Status:
- Updated: 6/9/2025