    Sanitary Sewer Projects

    Woodville Rd. Sewer Line Improvements

    City Job No. 411-DE-1612

    This project began as a sewer replacement project, then developed into a road reconstruction, including roundabouts at two locations (Old Hearne & SH 6 overpass). Shared use path, Sidewalks, & storm sewers. Because of ROW reconstruction, coordination with TxDOT & AFA are required.

    Project Map in PDF Format

    General Information

    • Project Manager/City Contact: Pat Edwards
    • Alternate City Contact: Jayson Barfknecht

    Design

    • Funding Source: Sanitary Fund; Street Improvement Fund
    • Design Engineer: Rabon Metcalf Engineering
    • Contract Amount: $142,400.00

    Construction

    • CIP Budget: $3,134,000
    • Funding Source: General Fund; Transportation Fee; Sanitary Fund; Water Fund
    • Contractor: Larry Young Paving
    • Contract Amount: $4,127,862.05
    • City Inspector: P. Alan Mitchell
    • Status: Construction is anticipated to start Spring 2020.
    • Updated: 3/20/2020

    Greenbrier Subdivision Sewer Extension

    City Job No. 411-D4-1607

    This project consists of extending an 18-inch sewer line from Thornberry Dr. through City park property to the Riverstone Subdivision.  The extension is needed for future expansion of the sanitary sewer service area.

    Project Map in PDF Format

    General Information

    • Project Manager/City Contact: Jayson Barfknecht
    • Alternate City Contact: Paul Kaspar

    Design

    • Funding Source: Sanitary Fund
    • Design Engineer: O’Malley Strand Associates, Inc.
    • Contract Amount: $26,250.00

    Construction

    • Funding Source: Wastewater Fund
    • Contractor: Elliot Construction, LLC
    • Contract Amount: $265,829.50
    • City Inspector: Paul Kocman
    • Status: Construction is substantially complete.
    • Updated: 3/20/2020