Skip to main content

City of Bryan, Texas

facebook icon twitter icon instagram icon pinterest icon flickr icon youtube icon NextDoor icon
  • Get the latest news and events information from the City of Bryan delivered straight to your inbox.

  • x

    MORE
    INFO  ›

    x

    facebook icon twitter icon instagram icon pinterest icon flickr icon youtube icon NextDoor icon

    General Projects

    Bryan Midtown Park Improvements

    City Job No. 700-D0-1712/572-D1-1811

    This project is to provide improvements to the park.

    Bryan Midtown Park Project Map in PDF Format

    General Information

    • Project Manager/City Contact: Frank Clark
    • Alternate City Contact: Paul Kaspar

    Design

    • Funding Source: Capital Reserve Fund
    • Design Engineer: Mitchell & Morgan
    • Contract Amount: $2,622,79.05

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2002
    • Contractor: Palasota Contracting
    • Contract Amount: $2,756,991.50
    • City Inspector: Mike Nobles
    • Status: Phase 1B & 3A is complete. This will stay on until total project is complete
    • Updated: 12/10/2020

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2013
    • Contractor: Construction Rent-A-Fence
    • Contract Amount: $37,166.25
    • City Inspector: Alan Mitchell
    • Status: Phase 1C is approximately 97% complete.
    • The contractor has completed installation of the bullpen extensions and pop-up roof. After close-out of the remaining building permits, this project will be considered Substantially Complete. The contractor has a preliminary punch list (issued November 2021) and will receive the Final Punch List after a Punch Walk is scheduled
    • Updated: 01/07/2022

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2011
    • Contractor: Kelly Burt Dozer
    • Contract Amount: $719,901.58
    • City Inspector: Mike Nobles
    • Status: Phase 3E is complete. This will stay on until total project is complete.
    • Updated: 11/5/2020

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2017
    • Contractor: Palasota Contracting
    • Contract Amount: $3,667,960.00
    • City Inspector: Alan Mitchell
    • Status: Phase 3C is approximately 92% complete.
    • The contractor has received most materials for the remainder of lake drain installation and will complete that construction in the near future. Hydro-mulch seeding and grass establishment is planned in the next several weeks.
    • Updated: 01/07/2022

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2010
    • Contractor: Solitude Lake Management
    • Contract Amount: $45,000
    • City Inspector: Mike Nobles
    • Status: Phase 3B is complete. This will stay on until total project is complete.
    • Updated: 11/5/2020

     

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2003
    • Contractor: Marek Bros Construction, Inc.
    • Contract Amount: $544,000.40
    • City Inspector: Mike Nobles
    • Status: Phase 1D is complete. This will stay on until total project is complete.
    • Updated: 10/11/2021

     

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2010
    • Contractor: Palasota Contracting LLC
    • Contract Amount: $1,148,190.95
    • City Inspector: Alan Mitchell
    • Status: Phase 2 is approximately 75% complete.
    • Approximately 60% complete. The contractor will be providing an updated construction schedule for the last remaining items soon. A final color selection for the arch culvert will be sent soon.
    • Updated: 01/07/2022

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2024
    • Contractor: Palasota Contracting LLC
    • Contract Amount: $2,053,110.20
    • City Inspector: Alan Mitchell
    • Status: 3D is approximately 55% complete.
    • The contractor continues to work at a steady pace.
    • Updated: 01/07/2022

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2029
    • Contractor: Larry Young Paving, LLC.
    • Contract Amount: $4,996,227.06
    • City Inspector: Alan Mitchell
    • Status: 5A is approximately 24% complete.
    • The contractor continues at a steady pace to install utilities. Preparation for bridge delivery/installation has begun and continues to move quickly. The arch culvert bridge is on schedule to be delivered the second week of January.
    • Updated: 01/07/2022

    Railroad Quiet Zones Streetscaping

    City Job No. 332-D3-1108

    This project is to provide safety and acoustical improvements along the railroad corridor in Bryan.

    General Information

    • Project Manager/City Contact: Rachel Gaddis
    • Alternate City Contact: Paul Kaspar

    Design

    • Funding Source: Transportation Fund
    • Design Engineer: CTC, Inc.
    • Contract Amount: $22,698.00
    • Status: Complete

    Construction

    • Funding Source: General Fund Bonds
    • CIP Budget: $5,517,000.00
    • Contractor: Brazos Paving, Inc.
    • Contract Amount: $657,991.00
    • City Inspector: Alan Mitchell
    • Status: Approximately 40% complete.
    • Updated:  12/01/2021

     

    HOME

    MAIN MENU

    SEARCH

    DEPT. INFO

    HELP