    General Projects

    Edgewater Park Development

    City Job No. 572-D5-1615

    This project is to provide a complete design, including construction ready design, of amenities and features for Edgewater Park.

    Project Map in PDF Format

    General Information

    • Project Manager/City Contact: Patricia Edwards
    • Alternate City Contact: Sam Vernon

    Design

    • Funding Source: General Fund
    • Design Engineer: Halff & Associates
    • Contract Amount: $93,600

    Construction

    • Funding Source: General Fund
    • Contractor: JaCody Construction LP
    • Contract Amount: $1,195,502.37
    • City Inspector: Mike Nobles
    • Status: Construction is sub-complete.
    • Updated: 10/8/2020

    Bryan Midtown Park Improvements

    City Job No. 700-D0-1712/572-D1-1811

    This project is to provide improvements to the park.

    Bryan Midtown Park Project Map in PDF Format

    General Information

    • Project Manager/City Contact: Frank Clark
    • Alternate City Contact: Paul Kaspar

    Design

    • Funding Source: Capital Reserve Fund
    • Design Engineer: Mitchell & Morgan
    • Contract Amount: $2,622,79.05

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2002
    • Contractor: Palasota Contracting
    • Contract Amount: $2,756,991.50
    • City Inspector: Mike Nobles
    • Status: Phase 1B & 3A is approximately 95% complete. Contractor is continuing with site grading, utility installation, prepping building pads and parking lots
    • Updated: 10/8/2020

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2013
    • Contractor: Construction Rent-A-Fence
    • Contract Amount: $37,166.25
    • City Inspector: Mike Nobles
    • Status: Phase 1C is approximately 10% complete. Contractor is site grading, prepping building pad, utility installation, and parking lots. Change Order 1 was approved and allows for additional fill in 1 parking lot, chemical stabilization of baseball fields, and backstop wall to be added to each field.
    • Updated: 10/8/2020

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2011
    • Contractor: Kelly Burt Dozer
    • Contract Amount: $719,901.58
    • City Inspector: Mike Nobles
    • Status: Phase 3E is sub complete. Punchlist has been issued.
    • Updated: 10/8/2020

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2017
    • Contractor: Palasota Contracting
    • Contract Amount: $3,667,960.00
    • City Inspector: Mike Nobles
    • Status: Phase 3C is approximately 5% complete. Partial notice to proceed No.1 was issued 9/8/2020 for construction of haul roads & tire wash station. No. 2 is scheduled for 9/29/2020 NTP No.2 will include excavation and hauling of soil from the lake except areas as noted in ESI #1 & 2.
    • Updated: 10/8/2020

    Construction

    • Funding Source: 2020 Bonds-Fund 374
    • City Job No. 700-D0-2010
    • Contractor: Solitude Lake Management
    • Contract Amount: $45,000
    • City Inspector: Mike Nobles
    • Status: Phase 3B is approximately 35% complete.
    • Updated: 9/12/2020

    Railroad Quiet Zones Streetscaping

    City Job No. 332-D3-1108

    This project is to provide safety and acoustical improvements along the railroad corridor in Bryan.

    General Information

    • Project Manager/City Contact: Sam Vernon
    • Alternate City Contact: Paul Kaspar

    Design

    • Funding Source: Transportation Fund
    • Design Engineer: CTC, Inc.
    • Contract Amount: $22,698.00
    • Status: Letter of extension is being coordinated with CTC at this time, and awaiting FRA review of the Public Authority Application.

    Construction

    • Funding Source: General Fund Bonds
    • CIP Budget: $5,517,000.00
    • Contractor: TBD
    • Contract Amount: TBD
    • City Inspector: TBD
    • Status: Construction anticipated to start Fall 2021 – Spring 2022.
    • Updated:  10/8/2020

     

    Camelot Park Pedestrian Bridge

    City Job No. 572-D5-2006

    This project is to provide a bridge to link the walking trail from Briar Meadows Creek to the existing internal trail system within Camelot Park.

    Project Map in PDF Format

    General Information

    • Project Manager/City Contact: Kelly Sullivan
    • Alternate City Contact: Sam Vernon

    Design

    • Funding Source: TIRZ 19 Fund
    • Design Engineer: Bleyl Engineering
    • Contract Amount: $21,000

    Construction

    • Funding Source: General Fund
    • Contractor: Palasota Contracting
    • Contract Amount: $180,140.00
    • City Inspector: Alan Mitchell
    • Status: Construction is approximately 5% complete.
    • Updated: 10/8/2020